Tower crane wind limits

A tower crane does not have one wind limit. It has at least three, they are different numbers, and the one that catches people out is the lowest.

Three different questions

  • Working. The wind the machine may lift in, from the manual for that model.
  • Erecting, climbing and dismantling. A considerably lower figure, because the structure is not complete and sections are hanging in the air.
  • Out of service. What the crane must be left in when nobody is on it — jib free to weathervane, and the machine set up as the manual requires.

The erecting limit is the one that gets misread. People quote the working figure because it is the one they know, then plan a lift around it. On our own machines the limit for erecting, climbing and dismantling is well under the figure they work to in service, and the job sheet carries the erecting figure rather than the working one for exactly that reason.

Where the number comes from

The manufacturer's manual for that specific model. Not the standard, not a rule of thumb, and not the other crane in the yard — two machines from the same maker will not share a figure. If somebody quotes you a wind limit without naming the model, they are guessing.

What to do with the forecast

Check it against the erecting limit before anything leaves the yard, not on the morning. A lift that has to be stopped halfway because the wind came up is worse than one that was never started, and mobilising a mobile crane twice costs more than waiting a day.